Building Permit Processing Times by City

Data as of 2026-11-19 · 19 cities · permits issued 2025-11-20 to 2026-11-19 · Download CSV

Method

For each city, we measure the calendar days between the application or filing date and the issue date that the local permit source publishes, for permits issued in the trailing 12 months (2025-11-20 to 2026-11-19). Only issued permits are counted, so applications still under review are not in the sample. Each row shows the median, the middle half of permits (25th to 75th percentile) and the sample size. A permit is excluded when its source publishes no filing date, when it was issued before its filing date, or when the gap exceeds 1095 days. A city is excluded when half or more of its permits show the same filing and issue date (many sources publish a single date in both fields, which is not a processing-time measurement), when half or more lack a filing date, or when fewer than 100 permits remain. 573 sitemap-listed cities were excluded under these rules. Processing time depends on permit type and project scope; these figures describe the mix of permits each source published, not a promise for any individual application.

City Median days 25th–75th pct (days) Permits measured Newest issued
San Diego, CA 0 0–35 30,398 2026-11-17
Aurora, CO 1 0–8 15,316 2026-11-18
Cary, NC 1 0–3 5,645 2026-10-30
Grand Prairie, TX 1 0–18 3,094 2026-11-18
Lubbock, TX 1 0–37 5,263 2026-11-18
Medford, OR 1 0–9 859 2026-11-17
New Braunfels, TX 1 1–3 706 2026-11-03
Kansas City, MO 2 0–6 15,368 2026-11-14
Overland Park, KS 3 0–9 997 2026-11-18
Augusta-Richmond County, GA 4 1–13 1,538 2026-11-18
Fairfield, CA 6 1–26 1,204 2026-11-18
Allentown, PA 7 1–23 685 2026-11-18
New Orleans, LA 8 2–28 19,127 2026-11-18
Yakima, WA 8 0–29.5 247 2026-11-13
Bend, OR 16 6–65 1,914 2026-11-17
Cambridge, MA 16 5–38 1,497 2026-11-18
Santa Monica, CA 16 1–61 670 2026-11-17
Tallahassee, FL 23 14.5–41 327 2026-11-17
North Charleston, SC 45 31.5–166.5 135 2026-11-19

Use this data

Free to cite with attribution to PermitGrab. Suggested credit:

Source: PermitGrab — "Building Permit Processing Times by City" (data as of 2026-11-19) — https://permitgrab.com/research/permit-processing-times

Turn a market pattern into a research workflow

Choose the source-bounded workflow that fits your work before starting a trial. Contractor and owner fields, where available, vary by public source and record.

Choose a research workflow →

Try a free permit research tool first

Choose markets for a Pro trial →
Choose your
market next