| 2026-06-02 | Suspended Scaffold | EAST 89 STREET | Application for the installation and use of suspended scaffold as per plans file… | - |
| 2026-05-28 | Sidewalk Shed | WEST 75 STREET | PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK … | $1,750 |
| 2026-05-26 | Suspended Scaffold | POWELLS COVE BOULEVARD | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE INSPECTION, NO CHANGE IN USE, EGRESS, … | - |
| 2026-05-26 | Suspended Scaffold | CORPORAL KENNEDY STREET | HOIST INSTALLATION FOR ROOF REPAIRS, NO CHANGE IN USE, EGRESS, OR OCCUPANCY. | - |
| 2026-05-26 | Suspended Scaffold | POWELLS COVE BOULEVARD | OUTRIGGER SYSTEM INSTALLATION FOR FACADE REPAIRS. NO CHANGE IN USE, EGRESS OR OC… | - |
| 2026-05-26 | Suspended Scaffold | 162 STREET | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE INSPECTIONS, NO CHANGE IN USE, EGRESS,… | - |
| 2026-05-22 | Suspended Scaffold | POWELLS COVE BOULEVARD | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE INSPECTIONS, NO CHANGE IN USE, EGRESS,… | - |
| 2026-05-21 | Suspended Scaffold | 9 AVENUE | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE INSPECTIONS, NO CHANGE IN USE, EGRESS … | - |
| 2026-05-21 | Suspended Scaffold | 166 STREET | OUTRIGGER SYSTEM INSTALLATION FOR FACADE INSPECTION, NO CHANGE IN USE, EGRESS, O… | - |
| 2026-05-21 | Suspended Scaffold | 166 STREET | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE INSPECTIONS, NO CHANGE IN USE, EGRESS,… | - |
| 2026-05-20 | Sidewalk Shed | PLYMOUTH STREET | PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK … | $10,500 |
| 2026-05-20 | Suspended Scaffold | WEST 73 STREET | OUTRIGGER SYSTEM INSTALLATION FOR FACADE INSPECTIONS AND REPAIRS. NO CHANGE IN U… | - |
| 2026-05-19 | Suspended Scaffold | MT MORRIS PARK WEST | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE REPAIRS. NO CHANGE IN USE, EGRESS, OR … | - |
| 2026-05-18 | Suspended Scaffold | WEST 103 STREET | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE INSPECTION AND REPAIRS REPAIRS. NO CHA… | - |
| 2026-05-18 | General Construction | WEST 73 STREET | FACADE REPAIRS, INCLUDING TERRA COTTA AND CONCRETE PATCHING, AS WELL AS BRICK, T… | $68,050 |
| 2026-05-14 | Suspended Scaffold | WEST 36 STREET | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE REPAIRS AND OR INSPECTIONS. NO CHANGE … | - |
| 2026-05-14 | Sidewalk Shed | POWELLS COVE BOULEVARD | PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK … | $41,000 |
| 2026-05-12 | Sidewalk Shed | WEST 73 STREET | PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK … | $4,500 |
| 2026-05-11 | Supported Scaffold | WEST 73 STREET | INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS INDICATED ON PLANS. THERE WILL BE NO … | $100,000 |
| 2026-05-07 | General Construction | 98 STREET | IN UNIT 5P ON FLOOR 5, RENOVATION OF EXISTING BATHROOM FINISHES AS SHOWN ON PLAN… | $9,450 |
| 2026-04-27 | General Construction | WEST 103 STREET | Facade repairs, including helical tie replacement, as shown on the drawings file… | $341,350 |
| 2026-04-22 | Supported Scaffold | CARPENTER AVENUE | INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS INDICATED ON PLANS. THERE WILL BE NO … | $200,000 |
| 2026-04-17 | General Construction | BELL BOULEVARD | REPAIR AND/OR PATCHING TO THE UNDESIDE, TOPSIDE AND VERTICAL CONCRETE OF THE STR… | $154,648 |
| 2026-03-23 | General Construction | POWELLS COVE BOULEVARD | FACADE RESTORATION AT ALL ELEVATIONS, MASONRY REPLACEMENT ALONG W/WATERPROOFING … | $547,308 |
| 2026-03-23 | General Construction | PARK TERRACE EAST | Limited facade repairs at exterior face of masonry walls including brick field r… | $539,625 |
| 2026-03-05 | Sidewalk Shed | MADISON AVENUE | PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK … | $5,000 |
| 2026-02-26 | General Construction | WEST 81 STREET | Filing for facade repairs as per plans filed herewith. No change in use, occupa… | $50,000 |
| 2026-02-17 | Sidewalk Shed | WEST 103 STREET | PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK … | $12,600 |
| 2026-01-20 | General Construction | BAXTER STREET | REPLACE MAIN AND BULKHEAD ROOF, FACADE REPAIRS, BALCONY REPAIRS, AND RAILING REP… | $640,120 |
| 2026-01-02 | General Construction | EAST 89 STREET | ROOF REPLACEMENT AND FACADE, BALCONY, AND BULKHEAD REPAIRS. NO CHANGE IN USE, E… | $1,891,100 |
| 2025-12-02 | General Construction | PARK TERRACE WEST | Limited facade repairs at exterior face of masonry walls including brick field r… | $11,150 |
| 2025-11-17 | General Construction | 7 AVENUE | CANOPY AND OUTDOOR GRILLING AREA CONSTRUCTION AND PAVER INSTALLATION AT EXTERIOR… | $132,000 |
| 2025-10-16 | General Construction | WEST 107 STREET | Exterior repairs consisting of sealant application, stucco repairs , cutting & r… | $313,240 |
| 2025-06-27 | Sidewalk Shed | CENTRAL PARK WEST | PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK … | $10,000 |
| 2025-06-25 | Supported Scaffold | WEST 28 STREET | PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLDING AS PER PLANS SUBMITTED. WORK… | $150,000 |
| 2025-06-17 | Suspended Scaffold | WEST 36 STREET | OUTRIGGER SYSTEM INSTALLATION FOR INSPECTION & FACADE REPAIRS. NO CHANGE IN USE,… | - |
| 2025-06-02 | Suspended Scaffold | COLUMBIA STREET | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE REPAIRS. NO CHANGE IN USE, EGRESS, OR … | - |
| 2025-05-30 | Suspended Scaffold | COLUMBIA STREET | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE REPAIRS. NO CHANGE IN USE, EGRESS, OR … | - |
| 2025-05-27 | Suspended Scaffold | MADISON AVENUE | OUTRIGGERS SYSTEM INSTALLATION FOR FACADE REPAIRS. NO CHANGE IN USE, EGRESS, OR … | - |
| 2025-05-23 | Sidewalk Shed | COLUMBIA STREET | PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK … | $6,500 |
| 2025-05-09 | Sidewalk Shed | ROOSEVELT AVENUE | PROPOSED INSTALLATION OF A TEMPORARY SIDEWALK SHED AS PER PLANS SUBMITTED. WORK … | $7,000 |
| 2025-03-25 | General Construction | MADISON AVENUE | GENERAL CONSTRUCTION FOR LIMITED EXTERIOR FACADE REPAIRS INCLUDING PARAPETS, STO… | $1,150,000 |
| 2025-02-27 | Supported Scaffold | WEST 82 STREET | INSTALLATION OF PIPE SCAFFOLD AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN … | $10,000 |