| Date | Type | Address | Description | Value |
|---|---|---|---|---|
| 2026-04-17 | Site | 704 N G ST | BEGINNING AT TIE IN LOCATION WITH 0193920-TAC-3-TAC-OH-Rev 001, SPAN NEW (1) 96F… | - |
| 2026-04-16 | Site | 1301 TACOMA AVE S | BEGINNING AT TIE IN LOCATION FOR 0193920-TAC-7-???-?H-SEG 2-Rev 001 ON COURT E, … | - |
| 2026-04-16 | Site | 951 S SPRAGUE AVE | 1. INSTALL NEW 1/4" STRAND ONLY 2. INSTALL NEW DOWN GUY AND ANCHOR 3. INSTALL NE… | - |
| 2026-04-16 | Site | 2201 RUSTON WAY | FROM TIE IN LOCATION WITH CROWN CASTLE BSNF PERMIT AND O193920-TAC-11-TAC-OH-Rev… | - |
| 2026-04-16 | Site | 3806 N WATERVIEW ST | FROM THE TIE IN LOCATION FROM O193920-TAC-12-TAC-OH-SEG 1-Rev 001 OUTSIDE OF 380… | - |
| 2026-04-14 | Right-of-Way | 1104 S GRANT AVE | 1. INSTALL (1) 4" RISER PER DETAIL #1 ON SHEET 7. PULL (1) 432CT FIBER THROUGH. … | $94,000 |
| 2026-04-01 | Site | 2406 N 8TH ST | 1. SLACK SPAN - NEW 1/4" STRAND AND LASH (1) 864CT FIBER 2. INSTALL NEW 1/4" STR… | - |
| 2026-04-01 | Site | 724 N SHERIDAN AVE | 1. INSTALL NEW 1/4" STRAND AND LASH (1) 864CT AND (1) 96CT. 2. INSTALL NEW SPLIC… | - |
| 2026-04-01 | Site | 2116 N LAWRENCE ST | BEGINNING AT TIE IN LOCATION WITH O193920-TAC11-TAC-OH-Rev 001 AT N 28TH ST AND … | - |
| 2026-04-01 | Site | 1314 N 8TH ST | 1. INSTALL NEW 1/4" STRAND AND LASH (1) 96CT FIBER 2. INSTALL NEW DOWN GUY AND A… | - |
| 2026-04-01 | Site | 701 N CEDAR ST | 1. INSTALL NEW 1/4" STRAND AND LASH (1) 96CT FIBER 2. INSTALL NEW DOWN GUY AND A… | - |
| 2026-04-01 | Site | 820 N TACOMA AVE | BEGINNING AT TIE IN LOCATION WITH O193920-TAC-3-TAC-OH-Rev 001 CONTINUE TO SPAN … | - |
| 2026-04-01 | Site | 621 TACOMA AVE S | CONTINUING OFF OF O193920-TAC-7-TAC-OH-SEG 1-Rev 001, CONTINUE SPANNING NEW AERI… | - |
| 2026-04-01 | Site | 938 S GRANT AVE | 1. INSTALL NEW 1/4" STRAND AND LASH (1) 864CT FIBER 2. ATTACH TO EXISTING ANCHOR… | - |
| 2026-04-01 | Site | 3115 6TH AVE | BEGINNING AT THE TIE IN LOCATION WITH O193920-TAC-1-TAC-OH-Rev 001 ON 6TH AVE WE… | - |
| 2026-04-01 | Site | 2520 6TH AVE | ON THE SOUTHWEST CORNER OF OF THE INTERSECTION OF 6TH AVE AND THE ALLEY IN BETWE… | - |
| 2026-03-26 | Right-of-Way | 914 N PINE ST | INSTALL (1) NEW 2" RISER PER DETAIL 1 ON SHEET 7. PULL (1) 96CT FIBER THROUGH. T… | $75,000 |
| 2026-03-25 | Right-of-Way | 901 S SPRAGUE AVE | INSTALL (1) NEW 2" RISER PER DETAIL 1 ON SHEET 7. PULL (1) 864CT FIBER THROUGH. … | $58,000 |
| 2026-03-10 | Site | 2715 N ALDER ST | BEGINNING AT TIE IN LOCATION WITH O193920-TAC-10-TAC-OH-Rev 001 AT THE CORNER OF… | - |
| 2026-02-26 | Right-of-Way | 951 S SPRAGUE AVE | 1. INSTALL NEW 1/4" STRAND ONLY 2. INSTALL NEW DOWN GUY AND ANCHOR 3. INSTALL NE… | $16,685 |
| 2026-02-26 | Right-of-Way | 1314 N 8TH ST | 1. INSTALL NEW 1/4" STRAND AND LASH (1) 96CT FIBER 2. INSTALL NEW DOWN GUY AND A… | $17,211 |
| 2026-02-26 | Right-of-Way | 2201 RUSTON WAY | FROM THE TIE IN LOCATION FROM O193920-TAC-12-TAC-OH-SEG 1-Rev 001 OUTSIDE OF 380… | $29,551 |
| 2026-02-26 | Right-of-Way | 2406 N 8TH ST | 1. SLACK SPAN - NEW 1/4" STRAND AND LASH (1) 864CT FIBER 2. INSTALL NEW 1/4" STR… | $18,606 |
| 2026-02-26 | Right-of-Way | 1104 S GRANT AVE | 1. INSTALL (1) 2" RISER PER DETAIL #1 ON SHEET 7. PULL NEW 864CT FIBER THROUGH. … | $93,530 |
| 2026-02-26 | Right-of-Way | 724 N SHERIDAN AVE | 1. INSTALL NEW 1/4" STRAND AND LASH (1) 864CT AND (1) 96CT. 2. INSTALL NEW SPLIC… | $15,251 |
| 2026-02-26 | Right-of-Way | 701 N CEDAR ST | 1. INSTALL NEW 1/4" STRAND AND LASH (1) 96CT FIBER 2. INSTALL NEW DOWN GUY AND A… | $14,035 |
| 2026-02-26 | Right-of-Way | 2201 RUSTON WAY | FROM TIE IN LOCATION WITH CROWN CASTLE BSNF PERMIT AND O193920-TAC-11-TAC-OH-Rev… | $46,241 |
| 2026-02-26 | Right-of-Way | 938 S GRANT AVE | 1. INSTALL NEW 1/4" STRAND AND LASH (1) 864CT FIBER 2. ATTACH TO EXISTING ANCHOR… | $17,126 |
| 2026-02-20 | Right-of-Way | 2715 N ALDER ST | BEGINNING AT TIE IN LOCATION WITH O193920-TAC-10-TAC-OH-Rev 001 AT THE CORNER OF… | $49,331 |
| 2026-02-20 | Right-of-Way | 1718 S G ST | CONTINUING OFF OF O193920-TAC-7-TAC-OH-SEG 1-Rev 001, CONTINUE SPANNING NEW AERI… | $25,822 |
| 2026-02-20 | Right-of-Way | 2520 6TH AVE | ON THE SOUTHWEST CORNER OF OF THE INTERSECTION OF 6TH AVE AND THE ALLEY IN BETWE… | $18,417 |
| 2026-02-20 | Right-of-Way | 2116 N LAWRENCE ST | BEGINNING AT TIE IN LOCATION WITH O193920-TAC11-TAC-OH-Rev 001 AT N 28TH ST AND … | $27,255 |
| 2026-02-20 | Right-of-Way | 704 N G ST | BEGINNING AT TIE IN LOCATION WITH O193920-TAC-3-TAC-OH-Rev 001, SPAN NEW (1) 96F… | $31,764 |
| 2026-02-20 | Right-of-Way | 820 N TACOMA AVE | BEGINNING AT TIE IN LOCATION WITH O193920-TAC-3-TAC-OH-Rev 001 CONTINUE TO SPAN … | $43,435 |
| 2026-02-18 | Right-of-Way | 1718 S G ST | EGINNING AT TIE IN LOCATION FOR O193920-TAC-7-TAC-OH-SEG 2-Rev 001 ON COURT E, N… | $31,642 |
| 2026-02-17 | Right-of-Way | 3115 6TH AVE | BEGINNING AT THE TIE IN LOCATION WITH O193920-TAC-1-TAC-OH-Rev 001 ON 6TH AVE WE… | $28,236 |